The City of Modesto has enacted a Stormwater Ordinance in order to establish minimum stormwater management requirements and controls to protect and safeguard the general health, safety, and welfare of the public residing in watersheds within this jurisdiction. The City of Modesto is the permitting authority for all land disturbing activities and requires the land owner to maintain all on-site stormwater control facilities and all open space areas (e.g. parks or “green” areas) required by the approved stormwater control plan. The City of Modesto will only provide construction permits to projects that establish a plan to manage stormwater runoff occurring during the construction process. The City of Modesto, under the NPDES program, also has the authority to inspect properties for noncompliance and can issue a notice of violation (NOV) for any deficiency or infraction onsite. Property owners are responsible for the maintenance of any stormwater facilities or practices located on the property. The City of Modesto has the authority to inspect stormwater facilities and practices in order to ascertain that they are properly maintained and functioning.
‘The control measures, often termed Best Management Practices (BMPs), described in the 2011 Guidance Manual were selected to optimize post-construction, on-site stormwater pollution control. All Priority Projects must apply all four categories of stormwater pollution control measures: Site Design Control Measures (Section 4); Source Control Measures (Section 5); Low Impact Development Control Measures (Section 7); and Treatment Control Measures (Section 8).”
A post-construction Maintenance Plan shall be prepared and submitted to the City as part of the Project Stormwater Quality Control Measures Plan submittal. The Maintenance Plan should address items such as: Operation plan and schedule, including a site map; Maintenance and cleaning activities and schedule; Equipment and resource requirements necessary to operate and maintain facility; and Responsible party for operation and maintenance.
This section identifies basic information that shall be included in a Maintenance Plan.
Refer to Fact Sheets for individual control measures regarding device-specific maintenance requirements. Site Map Provide a site map showing boundaries of the site, acreage, and drainage patterns/contour lines. Show each discharge location from the site and any drainage flowing onto the site. Distinguish between soft and hard surfaces on the map. Identify locations of existing and proposed storm drain facilities, private sanitary sewer systems, and grade breaks for purposes of pollution prevention. With a legend, identify locations of expected sources of pollution generation (e.g., outdoor work and storage areas, heavy traffic areas, delivery areas, trash enclosures, fueling areas, industrial clarifiers, and wash-racks). Identify any areas having contaminated soil or where toxins are stored or have been stored/disposed of in the past. With a legend, indicate types and locations of stormwater control measures that will be built to permanently control stormwater pollution. Distinguish between pollution prevention, treatment, sewer diversion, and containment devices.
Baseline Descriptions List property owners and persons responsible for operation and maintenance of the stormwater control measures on-site. Include phone numbers and addresses. Identify intended method of funding (i.e., homeowners association fees) for operation, inspection, routine maintenance, and upkeep of stormwater control measures. List all permanent stormwater control measures. Provide a brief description of stormwatercontrol measure selected and, if appropriate, fact sheets or additional information.
As appropriate for each stormwater control measure, provide:
“Operational or facility conditions or changes that significantly affect the character or quantity of pollutants discharging into the stormwater control measures may require modifications to the Maintenance Plan and/or additional stormwater controls.”
“Create and maintain on-site, a log for inspector names, dates, and stormwater control measure devices to be inspected and maintained. Provide a checklist for each inspection and maintenance category. Perform and document annual testing of any mechanical or electrical devices prior to wet weather. Report any significant changes in stormwater control measures to the site management. As appropriate, assure mechanical devices are working properly and/or landscaped BMP plantings are irrigated and nurtured to promote thick growth. Note any significant maintenance requirements due to spills or unexpected discharges. As appropriate, perform maintenance and replacement as scheduled and as needed in a timely manner to assure stormwater control measures are performing as designed and approved. Assure unauthorized low-flow discharges from the property do not bypass stormwater control measures. Perform an annual assessment of each pollution-generating operation and its associated stormwater control measures to determine if any part of the pollution reduction train can be improved. Annual assessment reports must be submitted to the City.”
“If future correction or modification of past stormwater control measures or procedures is required, the owner shall obtain approval from the City prior to commencing any work. Corrective measures or modifications shall not cause discharges to bypass or otherwise impede existing stormwater control measures.”
Verification of maintenance provisions is required for all stormwater control measures specified in the2011 Guidance Manual, whether Site Design Control Measures (Section 4), Source Control Measures (Section 5), LID Control Measures (Section 7), or Treatment Control Measures (Section 8). Verification, at a minimum, shall include: The owner/developer’s signed statement accepting responsibility for inspection and maintenance until the responsibility is legally transferred. A sample Owners Certification statement is provided in Appendix D; and either. A signed statement from the public entity assuming responsibility for stormwatercontrol measure inspection and maintenance and certifying that it meets all City design standards; or Written conditions in the sales or lease agreement that require the recipient to assume responsibility for inspection and maintenance activities and to conduct a maintenance inspection at least once a year; or written text in project conditions, covenants, and restrictions for residential properties that assign maintenance responsibilities to the Home Owners Association for inspection and maintenance of stormwater control measures; or a legally enforceable maintenance agreement that assigns responsibility for inspection and maintenance of post-construction control measures to the owner/operator. A Maintenance Agreement with the City must be executed by the owner/operator before occupancy of the project is approved. Example Maintenance Agreement forms are provided in Appendix D.