Case Study

Multiphase Stormwater Infrastructure Rehabilitation in Atl. GA

Atlanta, GA

Atlanta, GA

Commercial

Stormwater Infrastructure Rehabilitation

Project Overview

A large commercial property experienced a significant stormwater system failure that began with a sinkhole and escalated into a collapse of a major pipe connection. The system included a 96-inch corrugated metal pipe transitioning into an 18-inch line located near active utilities and a transformer enclosure. The situation required immediate stabilization, emergency response and a long-term rehabilitation strategy, all while maintaining site operations and managing ongoing weather conditions.

After decades in service, key sections of the system were approaching the end of their expected lifespan. Deterioration within the pipe raised concerns about structural reliability, drainage performance and the potential for surface impact.

AQUALIS was brought in to take a comprehensive approach, evaluating the system, identifying critical failures and developing a clear path forward. By combining inspection, engineering insight and coordinated construction planning, the team positioned the project to move efficiently from assessment to repair while maintaining uninterrupted facility operations.

Due to the nature of the business, it was imperative the site stayed operational. This meant the rehabilitation process must be phased to allow for visitor entry. The sections of pipe ran across the main parking lot as well as the entrance. To safely conduct repairs and keep the building operational, AQUALIS developed a details action plan to repair the areas in sections allowing for parts of the parking lot to still be utilized.

Phase 1: Initial Investigation and Stabilization

The first phase focused on identifying the failure point and stabilizing the system to prevent further deterioration. A manhole in the parking lot was identified during this process as a point of failure. Crews used a combination of traditional excavation and hydro excavation to safely expose underground utilities and inspect pipe connections without causing additional damage. During this process, utility lines were encountered, requiring careful coordination to avoid service disruptions.

The structural weakness was identified at the connection between the pipe and the manhole. Crews installed a reinforced concrete patch to stabilize the junction and prevent further degradation while a comprehensive repair plan was developed. The area was then backfilled to protect from future deterioration. AQUALIS worked closely with the utility company to ensure power lines would not be damaged during the construction process or in the future. The asphalt was then repaired to allow for continued operations.

Sinkhole overview Screenshot-2026-06-11-143447-300x212_upscayl_4x_upscayl-standard-4x GAB (granular aggregated backfill) GAB Backfill Compacted Asphalt patch complete pre-constructions of work zones Screenshot-2026-06-11-144058-300x222_upscayl_4x_upscayl-standard-4x excavation continued setting up hydro excavation inside trench box hydro-excavation around the pipe 18" CMP lowered in place concrete connection between 18" & 96" flowable fill going in flowable fill completed Fresh soil imported for final backfill layer cleaning the site and removal of excess materials Screenshot-2026-06-11-150455-300x223_upscayl_4x_upscayl-standard-4x MH-8 broken lid removed Forming of new lid for MH-8 MH-8 lid installed parking spaces blacked off the previous evening injection point installed (below about 10') connection valves closed the entrance completed MH-4 required alteration to accommodate inversion process 24" CMP -view from outfall structure -view up -stream concrete bottom places and pre liner installed Inversion of the 24" line exiting the OCS CIPP after cured -view from MH to outfall grouting the CIPP joint at vault MH-4 after resoration

Phase 2: Emergency Sinkhole Repair and Pipe Replacement

The next phase of the project focused on a sinkhole. The location presented several challenges, including proximity to an active transformer enclosure, the presence of high-risk utilities and the need for confined space entry. Intermittent rain added complexity by increasing the risk of runoff and site instability.

Crews removed trees and demolished portions of the brick enclosure surrounding the transformer to allow safe access. Temporary construction barriers were installed to secure the area. Excavation proceeded directly above the failure point, supported by a trench box system to protect workers.

Hydro excavation exposed live power lines and the connection between the 96-inch pipe and the 18-inch line. The damaged pipe was found to be severely compromised and was removed in fragments. A new pipe section was installed and connection points were secured quickly in anticipation of incoming rain. The connection was reinforced with concrete bands and structural supports to ensure long-term stability.

Groundwater was managed through active pumping to maintain workable conditions. Backfilling was completed in controlled lifts to ensure proper compaction and structural integrity. Crews placed sand around exposed power lines and installed marking tape in accordance with utility requirements. Additional graded aggregate base was installed above the sand, along with a second layer of marking tape approximately 2.5 feet above the utilities.

Unusable material and stumps were removed, and clean fill was imported to restore the area. Crews then excavated and formed a footing for  brick enclosure, installed reinforcing steel and poured concrete. The transformer enclosure was rebuilt using brick and block construction to match existing architectural and visual aesthetics.


Phase 3: Systemwide Stabilization Through Geophysical Analysis and Grouting

Following the emergency repair, attention shifted to evaluating the broader system to prevent additional failures. A ground-penetrating radar study was conducted across approximately 550 feet of storm drain infrastructure beneath the parking lot. The study identified subsurface voids and weakened zones surrounding the pipe system.

Based on the findings, a targeted injection grouting plan was developed. Crews installed hollow steel rods at specific depths and injected a two-part grout mixture at controlled rates and pressures. The material expanded significantly upon injection, filling voids and stabilizing surrounding soils.

The grouting process was completed over nine days. Work was phased to limit disruption, with sections of the parking lot closed and reopened sequentially. Entrance access to the property was maintained through staged operations conducted over two days.


Phase 4: Structural Pipe Rehabilitation

To further strengthen the system, trenchless rehabilitation was performed using cured-in-place pipe lining. Minor excavation was required at one entry point, otherwise this repair option allowed minor disruption to the facility operation while. Four separate pipe runs were lined and steam-cured over four days, creating a continuous structural liner within the existing pipes.

This process restored structural integrity, improved hydraulic performance and extended the lifespan of the system. All joints were grouted to eliminate infiltration pathways and further reinforce the network.


Phase 5: Manhole Rehabilitation and Protective Coating

The final phase focused on restoring and protecting the large diameter (96”) corrugated metal pipe that served as underground detention for the system. The metal pipe was cleaned and prepared before the application of a high-strength spray-cast liner. This coating sealed multiple defects due to deterioration over time and poor original workmanship.  This now provides long-term protection against corrosion and structural degradation and an expected 50 year additional service life.


Results

The project stabilized the sinkhole, replaced the failed pipe and reinforced the broader stormwater system. Subsurface voids were eliminated, and the infrastructure was strengthened through a combination of excavation, grouting and trenchless rehabilitation. The phased approach allowed the property to remain operational throughout construction.

The system was tested shortly after completion during a significant rain event and performed as intended. The project demonstrated the importance of combining emergency response with long-term system rehabilitation to reduce risk and protect critical infrastructure.

 

Additional Case Studies