Stormwater Management
Comprehensive solutions for a wide range of above-ground and underground stormwater systems.
Wastewater Management
Ensure your wastewater system is operating efficiently with regular maintenance.
Sustainable Water Engineering
Comprehensive stormwater design in a cost efficient and sustainable manner.
Compliance & Consulting
Comprehensive solutions for a wide range of above-ground and underground stormwater systems.
Water Quality Testing
Comprehensive stormwater design in a cost efficient and sustainable manner.
Insights & Expertise
As the leader in the sustainable water industry, AQUALIS is able to provide insight and expertise to your project.


Case Study
Roswell, Ga.
Roswell, Ga.
Commercial
Stormwater Repairs
A commercial property in Roswell, Ga., experienced multiple structural failures in its underground stormwater network. One section of corrugated metal pipe (CMP) had lost part of its wall, a visible void raised concerns about the stability of the surrounding ground and another section had been deformed by a bollard, a short post installed to protect pavement and structures from vehicles. Sediment, debris and concrete obstructions further complicated access.
AQUALIS was brought in to help repair the failed sections and rehabilitate approximately 1,500 feet of stormwater pipe using cured-in-place pipe (CIPP) lining, a method that creates a new pipe inside the existing one.
CMP is common beneath commercial properties because it is lightweight and easy to install. Over time, the metal can corrode, particularly along the bottom of the pipe where water and sediment accumulate. As the walls thin, the pipe loses structural strength, increasing the risk of failure.
At the Roswell property, deterioration had progressed beyond routine maintenance. One pipe section had an opening where the metal wall had deteriorated, creating a pathway for soil to enter the drainage system. A visible void at a second location raised concerns about ground settlement and potential sinkhole formation. A third section had been pushed out of its original circular shape by a bollard, raising the question of whether it needed to be excavated and replaced.
Access presented another challenge. Accumulated sediment, debris and concrete obstructions prevented closed-circuit television (CCTV) inspection cameras from traveling through certain pipe segments. A buried manhole between two catch basins further limited entry into the network.
With structural failures at multiple locations and deterioration throughout the remaining pipes, replacing the entire network would have required extensive excavation. The project instead called for targeted repairs followed by trenchless rehabilitation to address the damage while limiting disturbance to the commercial property.
Restoring access. Crews excavated to expose the buried manhole, establishing an additional entry point into the system. High-pressure water jetting loosened accumulated sediment and debris, while vacuum equipment removed the material. Clearing the obstructions improved access for CCTV inspection and prepared the pipes for lining. A clean interior was essential to prevent debris from interfering with liner installation.
Evaluating the deformed section. Once cameras could reach the bollard-damaged pipe, AQUALIS assessed the extent of the deformation. The team determined the section remained sound enough to line in place, avoiding an additional excavation.
Replacing the failed sections. Crews excavated two locations and replaced the damaged pipe. The repairs closed the opening left by the deteriorated pipe wall and addressed the damaged area associated with the visible void. Excavated areas were backfilled and compacted to restore support around the repaired infrastructure.
Lining the remaining network. With the structural repairs complete, AQUALIS installed approximately 1,500 feet of CIPP liner throughout the remaining network, including the deformed section. Crews inserted a flexible, resin-saturated liner into the existing pipes and cured it until it hardened into a continuous interior structure. The new liner reinforced the aging infrastructure and provided a corrosion-resistant interior without requiring excavation along the full length of the network.
Following installation, crews conducted post-repair CCTV inspections, restored disturbed surfaces and removed material collected during cleaning and excavation.
The completed rehabilitation restored the property’s underground stormwater network while preserving much of the existing developed surface. Excavation was concentrated at the failed sections and necessary access points, avoiding the widespread ground disturbance associated with replacing the entire network. Lining the bollard-damaged section in place eliminated one more dig.
The repaired pipes and continuous CIPP lining restored structural integrity and stormwater conveyance, addressing deterioration that could have contributed to further soil loss and ground settlement.
Problems like the ones at the Roswell property rarely start as emergencies. A small opening in a pipe wall can take years to become a void beneath the pavement. Pavement that dips near catch basins, water that pools after storms and sediment that keeps returning to inlets can all signal damage below. Catching those signs early can mean saving more of the existing system with repairs rather than replacements.
AQUALIS helps property teams evaluate aging stormwater infrastructure, address structural deficiencies and develop rehabilitation plans based on existing system conditions. Contact AQUALIS to discuss stormwater inspection, repair and rehabilitation options for your property.